Past Projects
Past Projects
Project: D. Miller Stream Restoration
Date Completed: Completed in June 2026
Stream: Little Conowingo Creek, Conowingo Watershed
Location: Goat Hill Rd, Peach Bottom – South side of road
Project Goal: 3,400 ft- Stream bank fencing (both sides); 3.77acres - Forest buffer installation;
Work Done: 3,400 ft- Stream bank fencing (both sides); Bank stabilization (8 rock vanes, 47 rock deflectors, 1 rock cross-vane, 7 boulder walls, bio-engineering); In-stream fish habitat structure (17 mudsills); 3 - Livestock crossings; Large floodplain bench (legacy sediment removal)
Annual Reduction: Nitrogen – 255 lbs.; Phosphorus – 231.2 lbs.; suspended solids- 76.3 tons
Total Cost: $832,440 (includes D Lapp Project)
Contractor: Flyway Excavating and Rettew Engineering
Project Cost:Funded By: PA DEP through EPA 319 Clean Water Act
Project: D. Lapp Farm Stream Restoration
Date Completed: June 2023
Stream: Unnamed Tributary, Conowingo Watershed
Location: Maxwell Dr. Quarryville
Project Goal: 1,200 ft re-aligned and restored stream; 1.2 ac forest buffer
Work Done: 10 rock vanes, 21 root wads, 1 rock cross-vane, 2 - Livestock crossings; filling of old channel sections; approx. 2,500ft of streambank fencing
Annual Reduction: Nitrogen - 117lbs.; Phosphorous - 106lbs.; suspended solids - 35tons
Project Cost: $832,440 (includes D Miller Project)
Contractor: Flyway Excavating and Rettew Engineering
Funded By: PA DEP through EPA 319 Clean Water Act
Project: Neff-Dellinger Stream Restoration
Date Completed: March 2025
Stream: Dellinger Run; Chiques Creek Watershed
Location: Fairview Rd, Manheim
Project Goal: 2,800 linear ft stream restored; 5.1 AC Riparian Forest
Annual Reduction: Sedimentation: 183lbs, Nitrogen 150lbs, Phosphorus 42lbs
Work Done: Installed 6 log vanes, 90 linear ft mud sills, 840 linear ft of rock deflectors, 9 cross vanes, 3 channel blocks, 275 linear ft of toe boulders, 180 linear ft of rock walls, 10,000 ft of bank stabilization, one at-grade slat concrete crossing,
Annual Reduction: Nitrogen – 210 lbs., Phosphorus – 190 lbs., Suspended solids – 62.8 tons
Project Cost: $217,500
Contractor: Flyway Excavating and Rettew Engineering
Funded By: Lancaster Clean Water Partners (CAP – Countywide Action Plan) and Lancaster Conservation District
Project - Shearers Creek, Andy Ill’s property
Date - Summer and Fall of 2024
Location -
Project Goals - The project consisted of BMPs installed over 735 feet of stream to improve habitat, provide bank stabilization structures, remove invasive species of plants and trees, and installation of native trees and shrubs. Additionally, 1,075 feet of dirt and gravel road was required in the proposal to eliminate erosion of the farm lane.
Work Done -10 mudsills totaling 815 linear feet, 1 log cross vane & 4 rock cross vanes, 2 root wad deflectors, 1,075 feet road dirt and gravel, 4 random boulder clusters, restore 8 riffles, 215’ rock toe, 280’ bank grading ( to create a flood plain), 140’ brush mattress (to control erosion) and repair one crossing.
The project improves water quality and enhances wild trout habitat throughout the reach of this project and the downstream receiving waters. The site contains high value wetland habitat throughout the project area and some areas outside of it.
Work to be completed - establish 15 acres of buffer and remove invasives
Project Cost - $75,000
Funding Source - York & Lancaster Counties Habitat Improvement Grant Program
Before
After

